Comparative Analysis of Variables Causing Delays in the Construction of the Wiego Warehouse Building, Jalan Letda Sujono, Medan
(1) Universitas Islam Sumatera Utara
(2) Universitas Islam Sumatera Utara
(3) Universitas Islam Sumatera Utara
Corresponding Author
Abstract
Construction projects are of course carried out in accordance with the implementation plan which is prepared based on the letter of agreement, general contract conditions, special contract conditions and technical specifications. In this plan, it is determined when the project must start and when the project must be finished. In every construction project, of course all parties involved want the project to be completed on time as previously determined. However, in reality, projects have their own problems and obstacles. One of the problems that really affects project performance in terms of time, quality and cost is the problem of project delays. In this study, a case study was carried out regarding the identification and analysis of factors causing delays in work on the Wiego Warehouse Building Construction project so that from the results of the analysis of factors causing delays, dominant factors and responses to handling them can be obtained. The Wiego Warehouse building is located on Jalan Letda Sujono, Medan and was built by contractor PT. Mitra Mandiri Asset Indo. This became the basis for conducting this research. The aim of this research is to determine the causes/risk factors that have a high level (dominant) and risk management responses that have a high level, in order to improve contractor performance. The research used is descriptive, using a questionnaire as a research instrument. Study of factors causing delays using the risk frequency scale, risk impact scale, and risk analysis matrix. The research results show that risk events are included in the classification of causal factors/high risk (high risk), which are significant for the problem of delays in building project implementation and the handling response to risk events that have a high ratio level. The dominant factor factor causing delays has a Severity index value of 61% - 80% and a risk level value of 16 (sixteen). For handling, there are several handling actions for dominant risks. Handling is carried out to minimize factors that cause delays and avoid sanctions or fines.
Keywords
References
Anggi Eka Fahlevi., dan Ferry Safaria. (2019). Analisis Manajemen Risiko Pelaksanaan Proyek Konstruksi.
Arikan, M. and Dikmen (2004). ‘‘Construction Engineering and Management, Lecture Notes’’.
Devi Suryono, Saifoe El Unas, Eko Andi Suryo. (2016). Analisis risiko penggunaan analisa harga satuan pekerjaan beton bertulang yang sama untuk elemen bangunan yang berbeda.
Emmett J. Vaughan; the late, Curtis M. Elliot (1978). Fundamental of risk and insurance.
Fahmi Assagaf, Y., Fais Assagaf, S. S., Chairul Basrun Umanailo, M., Abdurrahman Basalamah, J., & Corresponding, M. (2022). Studi Evaluasi Keterlambatan Proyek Peningkatan Jalan Hotmix Lala-Karang Jaya (Study of Delay Evaluation of the Hotmix Lala-Karang Jaya Road Improvement Project).
Jordy Ladjao, Edwin Yurianto, Sentosa Limanto, Endro Wicakson. (2016). Analisis faktor penyebab keterlambatan pada bangunan tinggi di surabaya
Labombang, Mastura (2011), “Manajemen Risiko dalam Proyek Konstruksi”.
Monalisa Br. Siahaan, F. (2021). Analisis Faktor Penyebab Keterlambatan Proyek KonstruksiPada Pt. Pln (Persero) Uip Sumbagut.
Prianto Wibowo, Nikko Rozy. (2020). Analisis manajemen konstruksi pembangunan gedung rawat inap kelas iii rsud waled kabupaten Cirebon.
Sofiyan siregar. (2013 – 25). Metode Pemilihan Kuantitatif: Dilengkapi dengan Perbandingan Perhitungan Manual & SPSS Edisi Pertama.
Sugiyono. (2022). Metode Penelitian Kualitatif, (2022:131).
Sugiyono. 2013. Metode Penelitian Pendidikan Pendekatan Kuantitatif, Kualitatif, dan R&D.
Syamsul dwi maarif (2023). Tahapan Proyek Konstruksi dari Perencanaan Hingga Pelaksanaan.
Yunita Afliana Messah., Theodorus Widodo., Marisya L.Adoe (2013). Kajian penyebab keterlambatan pelaksanaan proyek konstruksi Gedung di kota Kupang.
Article Metrics
Abstract View : 48 timesPDF Download : 30 times
DOI: 10.57235/qistina.v3i2.4235
Refbacks
- There are currently no refbacks.
Copyright (c) 2024 Muhammad Risky Qamad Siregar, Jupriah Sarifah, Ronal H T Simbolon
This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.